Expect Delays Thursday At Lancaster, Betz On US 95

You can expect minor delays at US 95's intersection with Lancaster and Betz roads on Thursday. Avista Utilities will be continuing to relocate a transmission line along the highway.

Crews will be pulling a transmission line across 95 from 9-11 a.m. Traffic on 95 will be stopped for 2-3 minute intervals, approximately three times. Traffic on Lancaster and Bentz also will be affected.

The transmission line is located north of Hayden on state right-of-way, which is part of the U.S. 95 Wyoming to Idaho 53 highway widening known locally as "the Gap" project.

The $6 million project will widen approximately two miles of U.S. 95 to four lanes.