4th Street Project Starts Tuesday

The 4th Street Improvement Project will begin Tuesday, May 26th. It is a major revitalization effort, including enhancement of the midtown area.

There will be three phases to the 4th Street Improvement Project. This first phase will begin at Foster Avenue and end at Miller Avenue. The second phase, starting in late June, will begin at the alley north of Lakeside Avenue and proceed north to Foster Avenue. The final phase starts in mid to late July, beginning from Miller Avenue north to Harrison Avenue.

There will be one-lane, through traffic, throughout most of the project phases. Temporary closures, with detours to side streets, will occur when stormwater mains, water service lines, or accented intersections are being installed, or paving is taking place.